UNIQUE CHALLENGES
The challenge of this project was to implement changes to the counter system including removing a 10′ section of the existing counter building a new wall assembly with a secure door and fabricating an ADA counter height using recycled materials from the removed section of counter. All work was completed after 5 PM. Also, had to maintain access for public use on a daily basis.
CLIENT TESTIMONIAL
It’s great. The new glass panel blocks the wind, and it keeps us warm.
IDAHO FISH & GAMEMichael Maffey
PROJECT DETAILS
Name of Property: Idaho Department of Fish and Game-Headquarters
Address: 600 S Walnut St, Boise, ID 83712
Tenant: Idaho Fish and Game
Building/Project Manager: Michael Maffey
Budget: $23,000.00
Date of Project: July 2017
Time Frame: 30 Days
Unique Aspects: Maintaining public access to customer service desk.